Sanle fiber cement board installation process

2023-03-02 16:17:45
times

Processing method


Sanle cement fiber board has good machinability, can be arbitrarily cut, nail, drill and other construction according to the needs of the project.


1. Score the surface of the board as needed, then press open the board with a flattening tool.


2. Cut the board with a tile cutter.


3. Install the plate with an electric screwdriver.


4. Machining with electric boundary knife.


Exterior wall installation steps:


(1) Cleaning work Cleaning work site, cleaning work face; Clean the surface of the wall floating ash, oil, keep clean, clean.


(2) The position of hot-dip galvanized corner code on the side wall is determined according to the requirements of the design drawing.


(3) Reservation of equipment box doors and holes Reservation of equipment box doors and holes in advance.


(4) The installation of hot-dip galvanized Angle code is drilled on the side wall according to the position of the spring line, and then the hot-dip galvanized Angle code is firmly fixed on the side wall with non-embroidered steel expansion screws.


(5) The installation of L-type aluminum alloy keel is fixed by connecting the keel with the hot-dip galvanized Angle code with stainless steel bolts.


(6) Keel Yin and Yang Angle treatment in the keel Yin and Yang Angle position, with a long L-shaped aluminum Angle through the rivets to fix the two keels, so that the entire keel system more stable.


(7) The installation of the back pendant is fixed with the back bolt screws.


(8) The installation of the Sanle fiber cement board lifts the entire Sanle fiber cement board sideways, keeping the lower pendant just on the L-shaped aluminum alloy keel, and the upper pendant just on the L-shaped aluminum alloy keel above. The lower pendant is on the second L-type aluminum alloy keel, and the upper pendant is just on the L-type aluminum alloy keel;


(9) Gap treatment Fill 3mm sealant in the gap between the board and the board that has been hung.


(10) Subsequent installation The subsequent installation of Sanle fiber cement board refers to the above installation procedures, and leaves a 3mm gap, and the gap is filled with sealant. According to the construction drawings, Sanle fiber cement board top node processing, ground node processing, Yin and Yang Angle processing and equipment node processing.


(11) Installation self-inspection and cleaning thoroughly check the installed Sanle fiber cement board to ensure that the board is not damaged. After the completion of the construction, remove the Sanle fiber cement board surface protective film, clean up the site, and deliver for acceptance.